State of Ghilotti Bros., Inc. – Reflecting on 2025. Looking Ahead to 2026.
As we enter 2026, Ghilotti Bros., Inc. does so with strong momentum, clear direction, and a foundation built for continued growth.
Coming off a very successful 2025, GBI begins the year with record breaking amount of new work booked during 2025, supported by a particularly strong paving workload. This mix allows projects to move quickly into production while maintaining a steady mix of work across our core services.
Equally important, the early part of the year provides the opportunity for detailed planning and coordination, ensuring projects are set up for efficient execution long before crews mobilize.
2025: Performance Across the Board
Throughout 2025, GBI delivered a diverse portfolio of civil infrastructure projects across Northern California, consistently meeting expectations for quality, safety, and schedule.
Major wins in Ukiah and Antioch, along with numerous regional projects, contributed to a record-breaking amount of new work booked during the year.
Key highlights from 2025 include:
- Highest sales volume in the company’s 112-year history, reflecting strong execution and market demand
- Recognition of GBI’s award-winning culture, including being named a Best Place to Work
- Continued leadership in safety, earning recognition for our best-in-class safety culture through UCON
- Delivery of award-winning projects across the region
- Entering 2026 with record backlog, positioning the company for continued momentum
Looking Ahead to 2026
With a strong foundation in place, GBI is focused on the opportunities ahead.
Several major infrastructure projects will help define the early part of the year, including:
- Route 101 Marin Paving Project – spanning from Greenbrae to Terra Linda, focused on ramp improvements and full mainline paving across one of Marin County’s busiest corridors.
- Route 4 Antioch Project – a seven-mile highway improvement effort including storm drainage upgrades, ramp and signal improvements, and rubberized asphalt paving to enhance safety and reliability.
- Highway 101 Ukiah Project – an eight-mile upgrade featuring shoulder widening, paving, and cable barrier replacement to improve long-term corridor performance.
Together, these projects represent meaningful opportunities to build on the success of 2025 while continuing to deliver high-quality infrastructure improvements across the region.
Leadership Growth & Organizational Development
As GBI continues to evolve, leadership development remains a priority.
In 2025 and early 2026, several key leadership advancements took place:
- Gino Ghilotti was promoted to Vice President of Organizational Development, supporting long-term alignment, organizational performance, and strategic growth
- Stephanie Taylor was promoted to Vice President of Talent, expanding her leadership over recruiting, employee development, and our intern program
- Tommy Elias transitioned from Superintendent to Special Projects Manager, bringing deep field experience into complex and specialized project delivery in our residential division
New Hires:
- Rushabh Lunkaad came on board as a Senior Estimator, further reinforcing the depth and competitiveness of our estimating team
- Clifton Evans joined the team as our new Safety Director furthering our commitment to an award-winning safety culture
These changes reflect intentional investment in leadership, experience, and continuity across the organization.
GBIU Mentor/Protégé Program
As we kick off the 2026 season, we’re excited to continue building momentum within GBIU (Ghilotti Bros., Inc. University) and the Mentor/Protégé Program. The program remains heavily focused on developing our field teams while also supporting growth opportunities across the broader organization.
As of year-end, 21 employees were actively enrolled and participating in the mentor program. Demonstrating strong engagement and meaningful progress.
Looking ahead to 2026, our goal is to grow the program by 20% while continuing to support intentional development pathways and well-earned promotions. Recent successes include:
• Jacob Locks — promoted to Foreman
• Chris George — promoted to Lead Dispatcher
• Nick Kristofors — promoted to Project Engineer
• Jeff Pearson — promoted to Project Engineer
• Justin King — promoted to Project Manager
• Federico Resendis — promoted to General Superintendent
Project Spotlights: Partnering, Innovation, and Problem Solving in the Field
A defining part of GBI’s work in 2025 was not just delivering projects, but solving complex challenges through collaboration, value engineering, and proactive partnership with owners and stakeholders.
Sonoma County Overlay Program
The Sonoma County Overlay Project was a countywide pavement preservation and infrastructure improvement program spanning more than 40 work locations and delivered under a compressed 100-day construction window.
From the outset, the County of Sonoma and GBI established a formal partnering framework with a neutral facilitator, recognizing that the scale, schedule constraints, and public interface would require constant coordination and rapid decision-making.
During construction, environmental permit approvals for ditch maintenance and culvert installations created potential schedule impacts. Rather than allowing work to stall, the team collaborated weekly to re-sequence unaffected areas, maintain production momentum, and jointly plan remobilization strategies. This proactive approach preserved schedule performance and minimized disruption to the traveling public.
Additional challenges — including redesign requirements at a smart railroad crossing and unsafe pavement drop-offs identified after completion of certain work areas — were resolved collaboratively through redesign, added shoulder backing, and coordinated safety improvements that enhanced final roadway quality and public safety beyond the original contract scope.
The project ultimately achieved zero OSHA recordable incidents, minimal rework, strong community feedback, and delivery within the contractual working-day framework while trending under budget — demonstrating the value of a true project-first partnering approach.
Napa Coombs Street Rehabilitation Project
The Napa Coombs Street Rehabilitation Project demonstrated GBI’s ability to deliver complex site development and roadway improvements within a constrained urban environment while maintaining strong partnership with the City of Napa and project stakeholders.
From the outset, the project team prioritized proactive coordination with the City, inspectors, and key trade partners, establishing a working relationship built on responsiveness, transparency, and shared project goals. This collaborative approach allowed field decisions to be addressed efficiently and kept construction aligned with both schedule and performance expectations.
During storm drain installation, the team encountered multiple conflicts involving existing underground utilities and elevation discrepancies that were not fully evident prior to construction. These conditions had the potential to disrupt productivity and delay the project if not resolved quickly.
Working closely with the City inspector, project engineer, and field crews, the GBI team verified elevations in real time and coordinated updated grade information for rapid engineering review. Storm drain alignments and elevations were then adjusted in the field to accommodate existing utilities while preserving drainage performance and design intent. This collaborative, real-time approach prevented downtime, avoided rework, and maintained installation progress despite unforeseen underground conditions.
In parallel, the project team coordinated extensively on paving phasing, section design, and placement sequencing. Through structured planning meetings between field leadership and paving management, the team refined the paving strategy to optimize constructability, production efficiency, surface quality, and overall project cost effectiveness.
Through strong agency partnering, disciplined coordination, and field-driven solutions, the Napa Coombs project successfully navigated underground conflicts and logistical challenges while maintaining schedule, quality, and budget objectives.
The project was ultimately recognized with the North Bay Business Journal’s 2025 Excellence in Construction Award, reflecting the team’s craftsmanship, coordination, and successful delivery in a challenging environment.
Presidio Trust Infrastructure Project
GBI’s recent work with the Presidio Trust highlighted the importance of proactive planning, collaborative problem solving, and field-driven value engineering when working in a historically sensitive and highly regulated environment.
Early in the project, a historic wall along West Pacific Avenue required protection prior to construction activities. Working collaboratively with the Presidio Trust, the project team quickly developed an efficient protection strategy using Triton water barriers. This approach provided the necessary structural protection while avoiding more complex temporary construction measures, saving both time and cost while preventing potential schedule delays.
During construction of multiple ADA-compliant ramps, the team also encountered unexpected elevation challenges that risked impacting accessibility requirements. Rather than allowing the issue to delay progress, GBI’s field and project teams evaluated conditions in real time and implemented immediate adjustments to achieve ADA compliance while maintaining our momentum.
These solutions reflected a shared commitment between GBI and the Presidio Trust to prioritize preservation, accessibility, and efficient delivery, demonstrating how strong partnering and responsive field leadership can resolve challenges quickly while protecting both project schedule and final quality.
Across all three projects, a common theme emerged: strong planning, transparent communication, and collaborative problem-solving lead to safer projects, better outcomes, and stronger partnerships.
Safety: Leading From the Front
Safety remains foundational to everything GBI does.
In 2025, GBI closed the year with zero recordable injuries and 1.7 million man hours without a lost time incident. A direct result of leadership engagement, field accountability, and a culture where safety is owned at every level.
With the addition of Safety Director Clifton Evans, GBI continues to strengthen its safety program through expanded Job Safety Analysis (JSA) participation, clearer accountability standards, and improved inspection processes across the fleet and field operations. Daily JSA tracking has increased visibility and reinforces proactive planning on every job, with a goal of achieving 100% JSA completion across projects in 2026.
The team also implemented a new Safety Accountability SOP to ensure consistent tracking of safety infractions and corrective actions, while standardizing equipment inspections through a QR Code-based mobile system to make compliance faster and more accessible for crews in the field.
In response to underground utility challenges across the industry, GBI has begun auditing and strengthening its utility-avoidance procedures, updating safety manual guidance, and expanding field training. The objective is clear: eliminate at-fault underground utility strikes moving forward.
GBI also continues investing in practical field solutions that protect crews day-to-day, including ergonomic tools such as powered wheelbarrows that reduce strain and help prevent overexertion injuries. As well as the implementation of Class II hard hats for field crews.
These results reflect a safety culture built on planning, communication, and accountability in the field every day. Our teams continue to lead from the front to ensure every employee goes home safe at the end of the day.
Investing in Technology & Innovation
GBI continues to invest in tools and technologies that improve how we plan, build, and deliver projects.
This includes expanded drone usage in the field to support project documentation, material tracking, and site visibility. GBI has also been an early adopter and investor in construction-focused technology companies such as Built Robotics, which is advancing autonomous heavy equipment, and Bulk Exchange, a platform improving how contractors’ source and manage bulk materials. Supporting innovation in these areas reflects our belief that the future of construction will be shaped by smarter equipment and more efficient supply networks.
GBI also continued working closely with EcoTerra, whose expanding materials operations, support sustainable construction practices across the region. Through this collaboration, projects benefited from increased use of recycled materials, local sourcing, and efficient delivery methods aligned with long-term sustainability goals.
At GBI, technology is not about trends, it’s about practical solutions that help us deliver safer projects, stronger partnerships, and consistent results.
Recognition, Community & Industry Impact
GBI’s work and culture continued to earn recognition in 2025 and early 2026.
The San Bruno Recreation and Aquatic Center project was recognized by Engineering News-Record (ENR) as Best Project of the Year in the Sports & Entertainment sector, highlighting collaboration, perseverance, and technical execution across the project team.
The Napa Coombs St Rehabilitation Project won North Bay Business Journals 2025 Excellence in Construction Award for our team’s craftsmanship and dedication.
Locally, GBI was honored with multiple 2026 Marin IJ Readers’ Choice Awards, including Best Family-Owned Business and Best Businessperson (Mike Ghilotti) along with honor awards for Best General Contractor, Best Place to Work, and Best Local Brand.
These recognitions reflect not only the projects we build, but the culture behind them.
What We’re Looking Forward To
As we move forward, GBI is focused on three main priorities:
- Delivering larger and more complex infrastructure projects with the same discipline and reliability that define our work
- Expanding smart and sustainable construction practices across divisions
- Continuing to develop our people, creating pathways for leadership, growth, and long-term careers
With a strong backlog, experienced leadership, and a skilled workforce, GBI is positioned for another year of meaningful progress.
We’re proud of what our teams accomplished in 2025 and grateful to the clients, partners, and communities who place their trust in Ghilotti Bros., Inc.
The work continues and we look forward to building what’s next.